home *** CD-ROM | disk | FTP | other *** search
/ Space & Astronomy / Space and Astronomy (October 1993).iso / mac / TEXT / DAILY_2 / 930604.DFC < prev    next >
Text File  |  1993-06-18  |  43KB  |  1,161 lines

  1.  
  2. "930604.DFC" (41535 bytes) was created on 06-04-93
  3.  
  4. 04-Jun-93 Daily File Collection
  5.    These files were added or updated between 03-Jun-93 at 21:00:00 {Central}
  6.                                          and 04-Jun-93 at 21:01:40.
  7.  
  8. =--=--=START=--=--= NASA Spacelink File Name:930604.REL
  9.  
  10. 6/4/93: STATION REDESIGN TEAM TO SUBMIT FINAL REPORT
  11.  
  12. Mark Hess
  13. Headquarters, Washington, D.C.                         June 4, 1993
  14.  
  15. RELEASE:  93-104
  16.  
  17.  
  18.         The Space Station Redesign Team, comprised of representatives from NASA
  19. and the international partners, will submit its final report on three space
  20. station options to the White House Advisory Committee on the Redesign of the
  21. Space Station on Monday, June 7, at the Stouffer Hotel in Crystal City, Va.
  22.  
  23.         The three options, the results of nearly 3 months of intensive research
  24. and analysis, include a modular concept that would use existing flight-proven
  25. hardware, a derivative of the current Space Station Freedom design and a space
  26. station that could be placed into orbit with a single launch of a
  27. Shuttle-derived vehicle.
  28.  
  29.         "The Team has done a tremendous job," said NASA Administrator Daniel
  30. Goldin. "They have developed 3 technically viable space stations.  Each
  31. provides for international cooperation, establishes a fully-capable space
  32. research center in orbit that will enable high priority science, technology and
  33. engineering research and in every case, do it for significantly less money than
  34. the current Space Station Freedom baseline."
  35.  
  36.         "The cost estimates provided by the Redesign Team reflect complete and
  37. accurate costs of each option and the current Space Station Freedom design," 
  38. Goldin said.
  39.  
  40.         The baseline Freedom cost numbers were subjected to rigorous review by
  41. an expert NASA team working apart from the Freedom program.  Those results,
  42. plus the costs of the three space station options, are being reviewed by an
  43. experienced, independent cost analysis team created by the White House advisory
  44. committee.
  45.  
  46.         "The estimates are honest and defensible.  They provide a solid basis
  47. for decision because they are comprehensive and compare all options on an
  48. apples- to-apples basis," Goldin said.  "Our books are open and will withstand
  49. the closest scrutiny."
  50.  
  51. President Directs Redesign
  52.  
  53.         An assessment early in 1993 by the incoming Administration determined
  54. the increases in the Space Station Freedom budget in the outyears would not fit
  55. within the expected NASA budget, which the Administration planned to cut by
  56. about 15 percent over the next 5 years in the interest of federal deficit
  57. reduction.  The White House also wanted to place increased emphasis on other
  58. NASA programs such as aeronautics and science.
  59.  
  60.         Rather than cancel the program, President Clinton directed NASA to
  61. redesign the space station and produce a configuration that would significantly
  62. reduce development, operations and utilization costs, while at the same time
  63. honor the United StatesU commitments to the international partners and provide
  64. the essential resources to advance the nationUs scientific and technology
  65. development capabilities in space.
  66.  
  67.         The Station Redesign Team also was charged with recommending new and
  68. streamlined management structures and acquisition strategies and to develop
  69. operational concepts that would cut operations costs in half.
  70.  
  71.         Monday's meeting will be the third and final public meeting with the
  72. Advisory Committee. Chaired by MIT President Dr. Charles Vest, the 16- member
  73. Advisory Committee will provide an independent assessment of the designs, cost,
  74. proposed management structure and the operations plan, and forward that
  75. assessment to the President on or about June 10.
  76.  
  77.         "The objective of the redesign team was to develop options for a
  78. redesigned space station," said Goldin. "The team was not asked to recommend
  79. one option over the others but rather to characterize each design's strengths
  80. and weaknesses in an unbiased manner."
  81.  
  82.         Directed by Deputy Associate Administrator for Space Flight and former
  83. astronaut Bryan O'Connor, the NASA team was led by a core group of about 36
  84. people.  The diversified team had at least one representative from each NASA
  85. center, several scientists and engineers with backgrounds that ranged from
  86. program managers to spacecraft designers.
  87.  
  88.         Ten representatives from the international partners - the European
  89. Space Agency, Japan and Canada - and from Italy formed the remainder of the
  90. core team.  Consultants from other government agencies and from industry served
  91. as advisors to the group.  The core team, working in Crystal City, Va.,
  92. received technical support on each of the options by people from across NASA.
  93.  
  94.  
  95. Station Objectives Outlined
  96.  
  97.         Goldin provided specific objectives and constraints, reflecting
  98. guidance from the Administration, to the team in an implementation letter of
  99. March 9, 1993.  In the letter, Goldin stressed that the redesigned space
  100. station must:
  101.  
  102. % Provide a cost effective solution to basic and applied research challenges
  103. whose merit is clearly indicated by scientific peer review, significant
  104. industrial cost sharing or other widely accepted method;
  105.  
  106. % Provide the capability for significant long-duration space research in
  107. materials and life sciences during this decade;
  108.  
  109. % Bring both near-term and long-term annual funding requirements within the
  110. constraints of the budget;
  111.  
  112. % Continue to accommodate and encourage international participation; and
  113.  
  114. % Reduce technical and programmatic risk to acceptable levels.
  115.  
  116.         Other directions to the team from Goldin included constraints or
  117. objectives of greatly reducing on-orbit assembly and checkout; planning for a
  118. shorter on-orbit lifetime (e.g., 10 years extendible to 15 years); greatly
  119. reducing the number of Shuttle launches and extravehicular requirements for
  120. deployment; advancing the permanently manned capability date; and
  121. reestablishing national leadership in space.
  122.  
  123.         In addition, the team was directed to give consideration to greater use
  124. of Shuttle and Spacelab capabilities (which may be modified to allow longer
  125. stays in orbit) and the Russian Mir space station.
  126.  
  127. Budget Guidelines Set
  128.  
  129.         In addition, Dr. John Gibbons, the PresidentUs Science Advisor,
  130. provided budget guidance for the Advisory Committee to use in their
  131. deliberations.  For the 5-year period from Fiscal Years 1994 to 1998, NASA was
  132. to assume a low option of $5 billion, a mid-range option of $7 billion and a
  133. high option of $9 billion.
  134.  
  135.         Activities which were to be paid for within the $5 billion, $7 billion
  136. and $9 billion accounts included: space station development, operations,
  137. utilization (including building science experiments and other payloads for the
  138. station and for Spacelab as well as the ground infrastructure to manage and
  139. deliver data to the users), Shuttle integration, facilities, research
  140. operations support, termination costs, transition costs and an appropriate
  141. level of reserves.
  142.  
  143. Three Main Options Evolve
  144.  
  145.         Option A is a modular build-up configuration which uses a combination
  146. of Space Station Freedom hardware and flight-qualified space systems from other
  147. sources, including the potential use of a self-contained DoD spacecraft called
  148. "Bus-1" to provide propulsion, guidance, navigation and control.  Option A
  149. includes a "Bus-1" configuration and a configuration without "Bus-1." Option A
  150. has four distinct phases of buildup including: Power Station (1
  151. photovoltaic(PV) array on-orbit for increased power to a docked
  152. orbiter/Spacelab); Human Tended Capability (adds U.S. laboratory);
  153. International Human Tended (adds an additional PV array and international
  154. elements); and Permanent Human Capability (adds third PV array, the U.S.
  155. habitat module and two Russian Soyuz ACRVs).
  156.  
  157.         Option B is derived from mature Space Station Freedom designs.  It
  158. makes maximum use of current systems and hardware to provide an incrementally
  159. increasing capability, emphasizing accommodations for users, adherence to
  160. international partner commitments, flexibility and growth potential, and
  161. recommends some system changes to save money.  Like Option A, the
  162. Freedom-derived option is built up over 4 stages.  From an assembly sequence
  163. standpoint, the primary difference between the Option A and B is that the
  164. Freedom-derived configuration adds the third PV array before the international
  165. partner elements are added.
  166.  
  167.         Option C is a single-launch space station.  This configuration features
  168. a 92- foot-long, 23-foot-diameter core module launched as part of a Space
  169. Shuttle vehicle and uses an existing external tank, solid rocket boosters and
  170. Shuttle main engines.  The module would provide 26,000 cubic feet of
  171. pressurized volume, separated into 7 "decks" connected by a centralized
  172. passageway.  Seven berthing ports would be located on the circumference of the
  173. module to place the international modules and other elements.
  174.  
  175.         "Each option is capable of accomplishing the mission of the space
  176. station," said Goldin. "All of them offer significant scientific and
  177. engineering research capabilities, especially in their permanently human
  178. presence stages."
  179.  
  180.         Goldin said all the options also would:
  181.  
  182. % make maximum use of Space Station Freedom systems and components, which have
  183. completed a rigorous critical design review, where it is both cost effective
  184. and schedule enhancing, thus benefiting from the nationUs investment to date in
  185. the Freedom program;
  186.  
  187. % incorporate changes that would reduce complexity and increase the probability
  188. for meeting cost and schedule;
  189.  
  190. % achieve substantial savings through a streamlined management structure that
  191. provides clear lines of authority, reduces overlap and gives accountability and
  192. authority to the lowest level to get the job done; and
  193.  
  194. % benefit from a new operations approach that would significantly reduce
  195. operational costs.
  196.  
  197.         Goldin said Russian hardware alternatives, where it could benefit the
  198. redesigned space station program, also were investigated.  In all three
  199. options, the Soyuz crew return vehicle has been baselined as the assured crew
  200. return vehicle.  Launch capability and other systems developed and in operation
  201. in the Russian space program are described in the report and will be considered
  202. for use in the redesigned space station or in future improvements.
  203.  
  204. -end-
  205.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  206. =--=--=-END-=--=--=
  207.  
  208. =--=--=START=--=--= NASA Spacelink File Name:930604.SHU
  209.  
  210. KSC SHUTTLE STATUS REPORT 6/4/93
  211.  
  212.  
  213.         KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
  214.                       Friday, June 4, 1993
  215.  
  216. KSC Contact: Bruce Buckingham       407-867-2468 (fax 867-2692)
  217. -----------------------------------------------------------------
  218.  
  219. Mission: STS-57/Spacehab/EURECA-Retrieval  Orbital Alt. 287 miles
  220. Vehicle: Endeavour/OV-105                 Inclination: 28 degrees
  221. Location: Pad 39-B                        Crew Size: 6
  222. Target Launch Date/Window: Around the third weekend of June
  223. Target KSC Landing Date/Time: TBD
  224. Expected Mission Duration: 7 days/23 hours (if cryogenics allow)
  225.  
  226. IN WORK TODAY:
  227. *  Secure new high pressure oxidizer turbopump (HPOTP) to main
  228.    engine 2
  229. *  Pressurization checks and trickle purge of Reaction Control
  230.    System and Orbital Maneuvering System
  231.  
  232. WORK SCHEDULED:
  233. *  Engine and HPOTP leak checks
  234. *  Helium Signature test
  235.  
  236. WORK COMPLETED:
  237. *  Bolted HPOTP to main engine 2
  238. *  Re-position body flap and main engines 1 and 3
  239. *  HPOTP powerhead checks
  240.  
  241. -----------------------------------------------------------------
  242. Mission: STS-51/ACTS-TOS/ORFEUS-SPAS      Orbital Alt.: 184 miles
  243. Vehicle: Discovery/OV-103                 Inclination: 28 degrees
  244. Location: OPF bay 3                       Crew Size: 5
  245. Mission Duration: 9 days/22 hours  Target Launch Period: mid-July
  246.  
  247. IN WORK TODAY:
  248. *  Orbiter aft compartment closeouts
  249. *  Orbiter mid-body closeouts
  250. *  External tank/solid rocket booster electrical checks in VAB
  251.    high bay 1
  252. *  Microwave landing system tests
  253.  
  254. WORK SCHEDULED:
  255. *  Orbiter/Forward Reaction Control System (FRCS) interface
  256.    verification checks
  257. *  Crew equipment interface tests
  258. *  Main landing gear functional checks
  259.  
  260. WORK COMPLETED:
  261. *  Freon coolant loop sampling
  262. *  External tank/solid rocket booster hard mate
  263. *  Orbiter/payload pre-installation and interface verification
  264.    tests
  265.  
  266. -----------------------------------------------------------------
  267. Mission: STS-58/SLS-2              Orbital Altitude: 176 miles
  268. Vehicle: Columbia/OV-102           Inclination: 39 degrees
  269. Location: OPF bay 2                Crew Size: 7
  270. Mission Duration: 14 days
  271. Target launch period: Early September
  272.  
  273. IN WORK TODAY:
  274. *  Operations to remove fifth cryogenic tank set
  275. *  Orbital maneuvering system hypergolic deservice preparations
  276. *  Auxiliary power unit catch bottle drain
  277. *  Configure payload bay for SLS-2
  278. *  Preparations to remove main engines
  279.  
  280. WORK SCHEDULED:
  281. *  Close OPF bay this weekend for hypergolic deservice operations
  282. *  Remove main engines
  283.  
  284. WORK COMPLETED:
  285. *  Remove and replace thruster from left OMS pod
  286.  
  287.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  288. =--=--=-END-=--=--=
  289.  
  290. =--=--=START=--=--= NASA Spacelink File Name:930604.SKD
  291.  
  292. Daily News/TV Sked 6-4-93 
  293.  
  294. Daily News
  295. Friday, June 4, 1993                  Two Independence Square, Washington, D.C. 
  296.     
  297. Audio Service: 202/358-3014     
  298.  
  299.  
  300.  % STS-57 mission update;
  301.  % Spacecraft Technology Briefing at Lewis;
  302.  % NASA exhibits at the Paris Air Show.
  303.  
  304.  
  305. Technicians at the Kennedy Space Center, in 
  306. preparation for the upcoming STS-57 mission, 
  307. plan to secure the new high pressure oxidizer 
  308. turbopump to main engine #2.  They will also 
  309. conduct pressurization checks and trickle purge 
  310. of the reaction control system and the orbital 
  311. maneuvering system.  Scheduled work on the 
  312. Space Shuttle Endeavour includes engine and 
  313. turbopump leak checks as well as conducting the 
  314. helium signature test.
  315.  
  316. At present, the targeted launch date is around the 
  317. third week in June.  Expected duration of the 
  318. mission is 7 days and 23 hours.
  319.  
  320. * * * * * * * * * * * * * * * *
  321.  
  322. NASA'S Lewis Research Center plans to host more 
  323. than 100 "decision makers" from industry and 
  324. government on June 8-9, 1993.  
  325.  
  326. The purpose of this Spacecraft Technology 
  327. Industry Briefing is to give a base for reshaping 
  328. technology development programs at the Lewis 
  329. Research Center and NASA to better serve the 
  330. customer's needs.  The participants will discuss 
  331. viewpoints in an open forum on topics including 
  332. communications, power propulsion and materials 
  333. and structures.
  334.  
  335. * * * * * * * * * * * * * * * *
  336.  
  337. With emphasis on environmental compatibility, 
  338. the NASA exhibit at this year's Paris Air Show will 
  339. focus on high speed research for a new 
  340. generation of airliners.  NASA will also exhibit a 
  341. 50-monitor videowall.  The video presentation 
  342. has participants discussing space station, space 
  343. technology, space science, space exploration and 
  344. aeronautics.  
  345.  
  346.  
  347. This year's exhibit theme, "A New Age of 
  348. Exploration--Expanding the Frontiers of Air and 
  349. Space for the Benefit of All" acknowledges the 
  350. many contribution of NASA's international 
  351. partners in human and robotic spaceflight and 
  352. the importance of the international cooperation 
  353. to help meet the challenges of the 1990's and 
  354. beyond.  The show dates for this years event are 
  355. June 10 - 20.
  356.  
  357. * * * * * * * * * * * * * * * *
  358.  
  359.  
  360.  
  361.         
  362. Here's the broadcast schedule for Public Affairs events on NASA TV.  
  363. Note that all events and times may change without notice and that all 
  364. times listed are Eastern. 
  365.  
  366.  
  367. Friday, June 4, 1993
  368.  
  369.         Noon    NASA Today news program.
  370.         12:15 pm        Aeronautics & Space Report.
  371.         12:30 pm        The Aeronauts.
  372.           1:00 pm       Shuttle Flow at KSC.
  373.           1:30 pm       Map the Martian World.
  374.           2:00 pm       NSTA Convention.
  375.           2:30 pm       Life on the Moon.
  376.           3:00 pm       Al Sherman on Quality.
  377.  
  378.         
  379.  
  380. NASA TV is carried on GE Satcom F2R, transponder 13, C-Band, 72 
  381. degrees West Longitude, transponder frequency is 3960 MHz, audio 
  382. subcarrier is 6.8 MHz, polarization is vertical.
  383.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  384. =--=--=-END-=--=--=
  385.  
  386. =--=--=START=--=--= NASA Spacelink File Name:6_10_9.TXT
  387.  
  388. 6/4/93: STATION REDESIGN TEAM TO SUBMIT FINAL REPORT
  389.  
  390. Mark Hess
  391. Headquarters, Washington, D.C.                         June 4, 1993
  392.  
  393. RELEASE:  93-104
  394.  
  395.  
  396.         The Space Station Redesign Team, comprised of representatives from NASA
  397. and the international partners, will submit its final report on three space
  398. station options to the White House Advisory Committee on the Redesign of the
  399. Space Station on Monday, June 7, at the Stouffer Hotel in Crystal City, Va.
  400.  
  401.         The three options, the results of nearly 3 months of intensive research
  402. and analysis, include a modular concept that would use existing flight-proven
  403. hardware, a derivative of the current Space Station Freedom design and a space
  404. station that could be placed into orbit with a single launch of a
  405. Shuttle-derived vehicle.
  406.  
  407.         "The Team has done a tremendous job," said NASA Administrator Daniel
  408. Goldin. "They have developed 3 technically viable space stations.  Each
  409. provides for international cooperation, establishes a fully-capable space
  410. research center in orbit that will enable high priority science, technology and
  411. engineering research and in every case, do it for significantly less money than
  412. the current Space Station Freedom baseline."
  413.  
  414.         "The cost estimates provided by the Redesign Team reflect complete and
  415. accurate costs of each option and the current Space Station Freedom design," 
  416. Goldin said.
  417.  
  418.         The baseline Freedom cost numbers were subjected to rigorous review by
  419. an expert NASA team working apart from the Freedom program.  Those results,
  420. plus the costs of the three space station options, are being reviewed by an
  421. experienced, independent cost analysis team created by the White House advisory
  422. committee.
  423.  
  424.         "The estimates are honest and defensible.  They provide a solid basis
  425. for decision because they are comprehensive and compare all options on an
  426. apples- to-apples basis," Goldin said.  "Our books are open and will withstand
  427. the closest scrutiny."
  428.  
  429. President Directs Redesign
  430.  
  431.         An assessment early in 1993 by the incoming Administration determined
  432. the increases in the Space Station Freedom budget in the outyears would not fit
  433. within the expected NASA budget, which the Administration planned to cut by
  434. about 15 percent over the next 5 years in the interest of federal deficit
  435. reduction.  The White House also wanted to place increased emphasis on other
  436. NASA programs such as aeronautics and science.
  437.  
  438.         Rather than cancel the program, President Clinton directed NASA to
  439. redesign the space station and produce a configuration that would significantly
  440. reduce development, operations and utilization costs, while at the same time
  441. honor the United StatesU commitments to the international partners and provide
  442. the essential resources to advance the nationUs scientific and technology
  443. development capabilities in space.
  444.  
  445.         The Station Redesign Team also was charged with recommending new and
  446. streamlined management structures and acquisition strategies and to develop
  447. operational concepts that would cut operations costs in half.
  448.  
  449.         Monday's meeting will be the third and final public meeting with the
  450. Advisory Committee. Chaired by MIT President Dr. Charles Vest, the 16- member
  451. Advisory Committee will provide an independent assessment of the designs, cost,
  452. proposed management structure and the operations plan, and forward that
  453. assessment to the President on or about June 10.
  454.  
  455.         "The objective of the redesign team was to develop options for a
  456. redesigned space station," said Goldin. "The team was not asked to recommend
  457. one option over the others but rather to characterize each design's strengths
  458. and weaknesses in an unbiased manner."
  459.  
  460.         Directed by Deputy Associate Administrator for Space Flight and former
  461. astronaut Bryan O'Connor, the NASA team was led by a core group of about 36
  462. people.  The diversified team had at least one representative from each NASA
  463. center, several scientists and engineers with backgrounds that ranged from
  464. program managers to spacecraft designers.
  465.  
  466.         Ten representatives from the international partners - the European
  467. Space Agency, Japan and Canada - and from Italy formed the remainder of the
  468. core team.  Consultants from other government agencies and from industry served
  469. as advisors to the group.  The core team, working in Crystal City, Va.,
  470. received technical support on each of the options by people from across NASA.
  471.  
  472.  
  473. Station Objectives Outlined
  474.  
  475.         Goldin provided specific objectives and constraints, reflecting
  476. guidance from the Administration, to the team in an implementation letter of
  477. March 9, 1993.  In the letter, Goldin stressed that the redesigned space
  478. station must:
  479.  
  480. % Provide a cost effective solution to basic and applied research challenges
  481. whose merit is clearly indicated by scientific peer review, significant
  482. industrial cost sharing or other widely accepted method;
  483.  
  484. % Provide the capability for significant long-duration space research in
  485. materials and life sciences during this decade;
  486.  
  487. % Bring both near-term and long-term annual funding requirements within the
  488. constraints of the budget;
  489.  
  490. % Continue to accommodate and encourage international participation; and
  491.  
  492. % Reduce technical and programmatic risk to acceptable levels.
  493.  
  494.         Other directions to the team from Goldin included constraints or
  495. objectives of greatly reducing on-orbit assembly and checkout; planning for a
  496. shorter on-orbit lifetime (e.g., 10 years extendible to 15 years); greatly
  497. reducing the number of Shuttle launches and extravehicular requirements for
  498. deployment; advancing the permanently manned capability date; and
  499. reestablishing national leadership in space.
  500.  
  501.         In addition, the team was directed to give consideration to greater use
  502. of Shuttle and Spacelab capabilities (which may be modified to allow longer
  503. stays in orbit) and the Russian Mir space station.
  504.  
  505. Budget Guidelines Set
  506.  
  507.         In addition, Dr. John Gibbons, the PresidentUs Science Advisor,
  508. provided budget guidance for the Advisory Committee to use in their
  509. deliberations.  For the 5-year period from Fiscal Years 1994 to 1998, NASA was
  510. to assume a low option of $5 billion, a mid-range option of $7 billion and a
  511. high option of $9 billion.
  512.  
  513.         Activities which were to be paid for within the $5 billion, $7 billion
  514. and $9 billion accounts included: space station development, operations,
  515. utilization (including building science experiments and other payloads for the
  516. station and for Spacelab as well as the ground infrastructure to manage and
  517. deliver data to the users), Shuttle integration, facilities, research
  518. operations support, termination costs, transition costs and an appropriate
  519. level of reserves.
  520.  
  521. Three Main Options Evolve
  522.  
  523.         Option A is a modular build-up configuration which uses a combination
  524. of Space Station Freedom hardware and flight-qualified space systems from other
  525. sources, including the potential use of a self-contained DoD spacecraft called
  526. "Bus-1" to provide propulsion, guidance, navigation and control.  Option A
  527. includes a "Bus-1" configuration and a configuration without "Bus-1." Option A
  528. has four distinct phases of buildup including: Power Station (1
  529. photovoltaic(PV) array on-orbit for increased power to a docked
  530. orbiter/Spacelab); Human Tended Capability (adds U.S. laboratory);
  531. International Human Tended (adds an additional PV array and international
  532. elements); and Permanent Human Capability (adds third PV array, the U.S.
  533. habitat module and two Russian Soyuz ACRVs).
  534.  
  535.         Option B is derived from mature Space Station Freedom designs.  It
  536. makes maximum use of current systems and hardware to provide an incrementally
  537. increasing capability, emphasizing accommodations for users, adherence to
  538. international partner commitments, flexibility and growth potential, and
  539. recommends some system changes to save money.  Like Option A, the
  540. Freedom-derived option is built up over 4 stages.  From an assembly sequence
  541. standpoint, the primary difference between the Option A and B is that the
  542. Freedom-derived configuration adds the third PV array before the international
  543. partner elements are added.
  544.  
  545.         Option C is a single-launch space station.  This configuration features
  546. a 92- foot-long, 23-foot-diameter core module launched as part of a Space
  547. Shuttle vehicle and uses an existing external tank, solid rocket boosters and
  548. Shuttle main engines.  The module would provide 26,000 cubic feet of
  549. pressurized volume, separated into 7 "decks" connected by a centralized
  550. passageway.  Seven berthing ports would be located on the circumference of the
  551. module to place the international modules and other elements.
  552.  
  553.         "Each option is capable of accomplishing the mission of the space
  554. station," said Goldin. "All of them offer significant scientific and
  555. engineering research capabilities, especially in their permanently human
  556. presence stages."
  557.  
  558.         Goldin said all the options also would:
  559.  
  560. % make maximum use of Space Station Freedom systems and components, which have
  561. completed a rigorous critical design review, where it is both cost effective
  562. and schedule enhancing, thus benefiting from the nationUs investment to date in
  563. the Freedom program;
  564.  
  565. % incorporate changes that would reduce complexity and increase the probability
  566. for meeting cost and schedule;
  567.  
  568. % achieve substantial savings through a streamlined management structure that
  569. provides clear lines of authority, reduces overlap and gives accountability and
  570. authority to the lowest level to get the job done; and
  571.  
  572. % benefit from a new operations approach that would significantly reduce
  573. operational costs.
  574.  
  575.         Goldin said Russian hardware alternatives, where it could benefit the
  576. redesigned space station program, also were investigated.  In all three
  577. options, the Soyuz crew return vehicle has been baselined as the assured crew
  578. return vehicle.  Launch capability and other systems developed and in operation
  579. in the Russian space program are described in the report and will be considered
  580. for use in the redesigned space station or in future improvements.
  581.  
  582. -end-
  583.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  584. =--=--=-END-=--=--=
  585.  
  586. =--=--=START=--=--= NASA Spacelink File Name:6_2_18_5.TXT
  587.  
  588.  NOTE: This file is too large {27855 bytes} for inclusion in this collection.
  589.     The first line of the file:
  590.  
  591. - Current Two-Line Element Sets #203 -
  592.  
  593.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  594. =--=--=-END-=--=--=
  595.  
  596. =--=--=START=--=--= NASA Spacelink File Name:6_7_2_14_2.TXT
  597.  
  598.  NOTE: This file is too large {18375 bytes} for inclusion in this collection.
  599.     The first line of the file:
  600.  
  601. HUBBLE SPACE TELESCOPE: A NEW VIEW OF THE UNIVERSE
  602.  
  603.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  604. =--=--=-END-=--=--=
  605.  
  606. =--=--=START=--=--= NASA Spacelink File Name:6_7_2_14_3.TXT
  607.  
  608.  NOTE: This file is too large {17951 bytes} for inclusion in this collection.
  609.     The first line of the file:
  610.  
  611. HST OBSERVER SPRING 1991
  612.  
  613.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  614. =--=--=-END-=--=--=
  615.  
  616. =--=--=START=--=--= NASA Spacelink File Name:6_8_3_4_26.TXT
  617.  
  618. MGN STATUS 6/3/93 
  619.  
  620. Magellan Status Report for 6-3-93 
  621.  
  622.  
  623. 1.  The Magellan Transition Experiment continues to go extremely well.
  624. The spacecraft has completed its "walk-in" phase to the desired
  625. aerobraking corridor. The spacecraft has made 70 atmospheric drag
  626. passes and the periapsis is now under 140.4 km and the apoapsis has
  627. been reduced below 7800 km.   All subsystems are reported to be
  628. nominal.  
  629.  
  630. 2.  The solar panels continue to increase by 40-45 degrees C during
  631. the drag pass, reaching a peak of 64 degrees C.  
  632.  
  633. 3.  Spacecraft controllers are considering performing the desat
  634. shortly before the drag pass in order to reduce the residual momentum
  635. and the resulting thruster activity.  This may reduce the propellant
  636. usage during the drag pass, even though the present usage is under the
  637. allocated amount.
  638.  
  639. 4.  The periapsis altitude will be raised about 800 meters by the
  640. first "1/2 up" COTM is now planned for orbit #7702  at 10:20 AM
  641. tomorrow.  However, it will continue its downward drift and require a
  642. series of 1/2 up COTMs at intervals of 4 to 9 days as the general
  643. downward drift continues.
  644.  
  645. COTM = Corridor Orbit Trim Maneuver
  646.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  647. =--=--=-END-=--=--=
  648.  
  649. =--=--=START=--=--= NASA Spacelink File Name:6_8_5_3_12.TXT
  650.  
  651. ULYSSES STATUS REPORT 139 & 140  APRIL 20-26, 1993
  652.  
  653.  
  654. ULYSSES STATUS REPORT 139
  655.  
  656. JET PROPULSION LABORATORY     
  657.  
  658. 27 April 1993
  659.  
  660. SUBJECT:  ULYSSES MISSION OPERATIONS REPORT No. 139
  661.  
  662. PERIOD:   20th April to 26th April 1993
  663.  
  664.  
  665. 1.   MISSION OPERATIONS
  666.  
  667.      Experiment reconfigurations have been carried out as required.
  668.  
  669.      On 20th April a routine KEP GAS monthly health check was performed.
  670.  
  671.      On 21st April a HED calibration was performed.
  672.  
  673.      On 26th April a KEP EPAC in-flight calibration was carried out.
  674.  
  675.      An Earth pointing manoeuvre was performed on 23rd April.
  676.  
  677.      An average of 96.2% data recovery was achieved during the reporting
  678.      period.
  679.  
  680.      The percentage of data acquired as a function of bit rate is as follows:
  681.  
  682.      1024 bps 44.3 %
  683.       512 bps 51.9 %
  684.  
  685. 2.   SPACECRAFT STATUS
  686.  
  687.      POWER
  688.  
  689.      Nominal.
  690.  
  691.      Estimated S/C power consumption 255 watts.
  692.  
  693.      AOCS
  694.  
  695.      Nominal.
  696.  
  697.      TTC
  698.  
  699.      The  spacecraft is currently configured with receiver  2  as
  700.      the  prime  unit  fed  via the high gain  antenna  and  with
  701.      receiver 1 as backup fed through the low gain antenna  (LGA-
  702.      F). The downlink is provided through EPC2/TWTA2.
  703.  
  704.      The  34  meter  ground stations are in use  to  support  TTC
  705.      operations.   Ranging from 34 meter or 70 meter antennas  is
  706.      once again routinely performed.
  707.  
  708.      Received downlink level -140 dBm.(34 meter) X-band.
  709.  
  710.      (Variations of up to 10 db. can be expected as a  result  of
  711.      station  antenna  in  use,  local  weather  conditions,  and
  712.      spacecraft antenna off-pointing).
  713.  
  714.      Received uplink level -122 dBm.
  715.  
  716.      DATA HANDLING
  717.  
  718.      Nominal.
  719.  
  720.      THERMAL
  721.  
  722.      Nominal.
  723.  
  724. 3.   FLIGHT DYNAMICS
  725.  
  726.      Solar  Aspect    The  angle increased from  10.76  on  Angle
  727.      (deg.)   20th April to 11.30 on 26th April.
  728.  
  729.      Sun-Probe-Earth   The angle increased from  10.62  on  Angle
  730.      (deg.)     20th April to 11.21 on 26th April.
  731.  
  732.      Spin Rate               4.978 rpm.
  733.  
  734. 4.   ORBITAL DATA
  735.  
  736.      Correction to last week's data which were in error:
  737.  
  738.      Data taken at 13:00 PDT on 19th April.
  739.      Distance from Earth                635,083,459 km.
  740.      Velocity relative to the Earth          86,639 km/hr.
  741.      Velocity relative to the Sun            37,221 km/hr.
  742.      Ecliptic latitude                         22.0 deg/south
  743.  
  744.      This week's data:
  745.  
  746.      Data taken at 13:00 PDT on 26th April.
  747.      Distance from Earth                646,502,166 km.
  748.      Velocity relative to the Earth          84,016 km/hr.
  749.      Velocity relative to the Sun            37,485 km/hr.
  750.      Ecliptic latitude                         22.5 deg/south
  751.  
  752. 5.   PLANNED OPERATIONS
  753.  
  754.      Routine  data  gathering operations will  continue  together
  755.      with experiment reconfigurations as required.
  756.  
  757.      On 27th April a SIM HET calibration will be carried out.
  758.  
  759.      A GRU program reload will be performed on 30th April.
  760.  
  761.      On  3rd May a KEP EPAC in-flight calibration will be carried
  762.      out.
  763.  
  764.      An  Earth  pointing manoeuvre will be carried  out  on  28th
  765.      April.
  766.  
  767. 6.   GROUND SEGMENT
  768.  
  769.      The  ground segment performed nominally during the reporting
  770.      period, with the exception of a period of bad data caused by
  771.      heavy rain in Madrid on 24th April.
  772.  
  773.  
  774.  
  775.  
  776.  
  777. ULYSSES MISSION STATUS REPORT  4/27/93
  778.  
  779. ULYSSES: The spacecraft is in a highly inclined solar orbit, now
  780. almost 30 degrees south (relative to the Sun's equator), in
  781. transit from its Jupiter gravity assist in February 1992 toward
  782. its solar polar passages (about 80 degrees south and north) in
  783. 1994 and 1995.  Ulysses spacecraft condition and performance are
  784. excellent, and cruise science data-gathering continues.  The
  785. Ulysses spacecraft was built by the European Space Agency and
  786. launched October 6, 1990 aboard Space Shuttle Discovery, with IUS
  787. and PAM-S stages.
  788.  
  789.  
  790.  
  791.  
  792.  
  793.  
  794. ULYSSES STATUS REPORT 140   APRIL 27 - MAY 3, 1993
  795.  
  796. JET PROPULSION LABORATORY       
  797.  
  798. May 10, 1993
  799.  
  800. ULYSSES MISSION OPERATIONS REPORT No. 140
  801.  
  802. PERIOD:   27th April to 3rd May 1993
  803.  
  804. 1.   MISSION OPERATIONS
  805.  
  806.      Experiment reconfigurations have been carried out as
  807.      required.
  808.  
  809.      On 27th April a SIM HET calibration was carried out.
  810.  
  811.      A GRU program reload was performed on 30th April.
  812.  
  813.      On 3rd May a KEP EPAC in-flight calibration was carried out.
  814.  
  815.      An Earth pointing manoeuvre was performed on 28th April and
  816.      3rd May.
  817.  
  818.      An average of 96.9% data recovery was achieved during the
  819.      reporting period.
  820.  
  821.      The percentage of data acquired as a function of bit rate is
  822.      as follows:
  823.  
  824.      1024 bps 56.08 %
  825.       512 bps 38.82 %
  826.  
  827. 2.   SPACECRAFT STATUS
  828.  
  829.      POWER
  830.  
  831.      Nominal.
  832.  
  833.      Estimated S/C power consumption 255 watts.
  834.  
  835.      AOCS
  836.  
  837.      Nominal.
  838.  
  839.      TTC
  840.  
  841.      The spacecraft is currently configured with receiver 2 as
  842.      the prime unit fed via the high gain antenna and with
  843.      receiver 1 as backup fed through the low gain antenna (LGA-
  844.      F). The downlink is provided through EPC2/TWTA2.
  845.  
  846.      The 34 meter ground stations are in use to support TTC
  847.      operations.  Ranging from 34 meter or 70 meter antennas is
  848.      once again routinely performed.
  849.  
  850.      Received downlink level -140 dBm.(34 meter) X-band.
  851.  
  852.      (Variations of up to 10 db. can be expected as a result of
  853.      station antenna in use, local weather conditions, and
  854.      spacecraft antenna off-pointing).
  855.  
  856.      Received uplink level -123 dBm.
  857.  
  858.      DATA HANDLING
  859.  
  860.      Nominal.
  861.  
  862.      THERMAL
  863.  
  864.      Nominal.
  865.  
  866. 3.   FLIGHT DYNAMICS
  867.  
  868.      Solar Aspect   The angle increased from 11.29 on Angle
  869.      (deg.)   27th April to 12.07 on 3rd May.
  870.  
  871.      Sun-Probe-Earth  The angle increased from 11.30 on Angle
  872.      (deg.)     27th April to 11.75 on 3rd May.
  873.  
  874.      Spin Rate               4.978 rpm.
  875.  
  876. 4.   ORBITAL DATA
  877.  
  878.  
  879.      Data taken at 13:00 PDT on 3rd May
  880.  
  881.      Distance from Earth                657,694,184 km.
  882.      Velocity relative to the Earth          81,556 km/hr.
  883.      Velocity relative to the Sun            37,692 km/hr.
  884.      Ecliptic latitude                         22.9 deg/south
  885.  
  886. 5.   PLANNED OPERATIONS
  887.  
  888.      Routine data gathering operations will continue togetherwith
  889.      experiment reconfigurations as required.
  890.  
  891.      On 5th May a HED calibration will be carried out.
  892.  
  893.      On 10th May a KEP in-flight calibration will be carried out.
  894.  
  895.      An Earth pointing manoeuvre will be carried out on 12th May.
  896.  
  897. 6.   GROUND SEGMENT
  898.  
  899.      The ground segment performed nominally during the reporting
  900.      period.
  901.  
  902.  
  903. ULYSSES MISSION OPERATIONS REPORT No. 141
  904.  
  905. PERIOD:   4th May to 10th May 1993
  906.  
  907. 1.   MISSION OPERATIONS
  908.  
  909.      Experiment reconfigurations have been carried out as
  910.      required.
  911.  
  912.      On 5th May a HED calibration was carried out.
  913.  
  914.      On 6th May a GRU reconfiguration took place.
  915.  
  916.      On 10th May a KEP in-flight calibration was carried out.
  917.  
  918.      No Earth pointing manoeuvre was performed during this
  919.      reporting period.
  920.  
  921.      An average of 95.5% data recovery was achieved during the
  922.      reporting period.
  923.  
  924.      The percentage of data acquired as a function of bit rate is
  925.      as follows:
  926.  
  927.      1024 bps 37.94 %
  928.       512 bps 57.26 %
  929.  
  930.      On 9th May a 14 minute loss of realtime data occurred due to
  931.      acquisition problems at Goldstone.
  932.  
  933. 2.   SPACECRAFT STATUS
  934.  
  935.      POWER
  936.  
  937.      Nominal.
  938.  
  939.      Estimated S/C power consumption 255 watts.
  940.  
  941.      AOCS
  942.  
  943.      Nominal.
  944.  
  945.      TTC
  946.  
  947.      The spacecraft is currently configured with receiver 2 as
  948.      the prime unit fed via the high gain antenna and with
  949.      receiver 1 as backup fed through the low gain antenna (LGA-
  950.      F). The downlink is provided through EPC2/TWTA2.
  951.  
  952.      The 34 meter ground stations are in use to support TTC
  953.      operations.  Ranging from 34 meter or 70 meter antennas is
  954.      once again routinely performed.
  955.  
  956.      Received downlink level -141 dBm.(34 meter) X-band.
  957.  
  958.      (Variations of up to 10 db. can be expected as a result of
  959.      station antenna in use, local weather conditions, and
  960.      spacecraft antenna off-pointing).
  961.  
  962.      Received uplink level -123 dBm.
  963.  
  964.      DATA HANDLING
  965.  
  966.      Nominal.
  967.  
  968.      THERMAL
  969.  
  970.      Nominal.
  971.  
  972. 3.   FLIGHT DYNAMICS
  973.  
  974.      Solar Aspect   The angle increased from 12.07 on Angle
  975.      (deg.)   4th May to 12.08 on 10th May.
  976.  
  977.      Sun-Probe-Earth  The angle increased from 11.81 on Angle
  978.      (deg.)     4th May to 12.13 on 10th May.
  979.  
  980.      Spin Rate               4.978 rpm.
  981.  
  982. 4.   ORBITAL DATA
  983.  
  984.      Data taken at 00:00:00 UTC on 10th May
  985.  
  986.      Distance from Earth                669,167,650 km.
  987.      Velocity relative to the Earth          79,728 km/hr.
  988.      Velocity relative to the Sun            37,930 km/hr.
  989.      Ecliptic latitude                         23.2 deg/south
  990.  
  991. 5.   PLANNED OPERATIONS
  992.  
  993.      Routine data gathering operations will continue together
  994.      with experiment reconfigurations as required.
  995.  
  996.      On 11th May a KEP RAM dump will be carried out.
  997.  
  998.      On 17th May A KEP in-flight calibration will be carried out.
  999.  
  1000.      An Earth pointing manoeuvre will be carried out on 12thMay.
  1001.  
  1002. 6.   GROUND SEGMENT
  1003.  
  1004.      The ground segment performed nominally during the reporting
  1005.      period with the exception of the problem at Goldstone
  1006.      reported above .
  1007.  
  1008.  
  1009. ULYSSES MISSION OPERATIONS REPORT No. 142
  1010.  
  1011. PERIOD:   11th May to 17th May 1993
  1012.  
  1013. 1.   MISSION OPERATIONS
  1014.  
  1015.      Experiment reconfigurations have been carried out as
  1016.      required.
  1017.  
  1018.      On 11th May a KEP RAM dump was carried out.
  1019.  
  1020.      On 17th May A KEP in-flight calibration was carried
  1021.      out.
  1022.  
  1023.      An Earth pointing manoeuvre was performed on 12th May.
  1024.  
  1025.      An average of 94.5% data recovery was achieved during
  1026.      the reporting period.
  1027.  
  1028.      The percentage of data acquired as a function of bit
  1029.      rate is as follows:
  1030.  
  1031.      1024 bps 47.28 %
  1032.       512 bps 47.21 %
  1033.  
  1034.      On 12th May a 2 hour 50 minute loss of realtime and
  1035.      playback data occurred due to antenna problems at the
  1036.      34 meter site at Goldstone.
  1037.  
  1038. 2.   SPACECRAFT STATUS
  1039.  
  1040.      POWER
  1041.  
  1042.      Nominal.
  1043.  
  1044.      Estimated S/C power consumption 255 watts.
  1045.  
  1046.      AOCS
  1047.  
  1048.      Nominal.
  1049.  
  1050.      TTC
  1051.  
  1052.      The spacecraft is currently configured with receiver 2
  1053.      as the prime unit fed via the high gain antenna and
  1054.      with receiver 1 as backup fed through the low gain
  1055.      antenna (LGA-F). The downlink is provided through
  1056.      EPC2/TWTA2.
  1057.  
  1058.      The 34 meter ground stations are in use to support TTC
  1059.      operations.  Ranging from 34 meter or 70 meter antennas
  1060.      is once again routinely performed.
  1061.  
  1062.      Received downlink level -142 dBm.(34 meter) X-band.
  1063.  
  1064.      (Variations of up to 10 db. can be expected as a result
  1065.      of station antenna in use, local weather conditions,
  1066.      and spacecraft antenna off-pointing).
  1067.  
  1068.      Received uplink level -122 dBm.
  1069.  
  1070.      DATA HANDLING
  1071.  
  1072.      Nominal.
  1073.  
  1074.      THERMAL
  1075.  
  1076.      Nominal.
  1077.  
  1078. 3.   FLIGHT DYNAMICS
  1079.  
  1080.      Solar Aspect   The angle increased from 12.08 on Angle
  1081.      (deg.)   11th May to 12.46 on 17th May.
  1082.  
  1083.      Sun-Probe-Earth  The angle increased from 12.17 onAngle
  1084.      (deg.)     11th May to 12.35 on 17th May.
  1085.  
  1086.      Spin Rate      4.978 rpm.
  1087.  
  1088. 4.   ORBITAL DATA
  1089.  
  1090.      Data taken at 00:00:00 UTC on 17th May
  1091.  
  1092.      Distance from Earth                682,091,226 km.
  1093.      Velocity relative to the Earth          78,408 km/hr.
  1094.      Velocity relative to the Sun            38,202 km/hr.
  1095.      Ecliptic latitude                         23.6
  1096.      deg/south
  1097.  
  1098. 5.   PLANNED OPERATIONS
  1099.  
  1100.      Routine data gathering operations will continue
  1101.      together with experiment reconfigurations as required.
  1102.  
  1103.      On 18th May a KEP GAS monthly health check will be
  1104.      carried out.
  1105.  
  1106.      On 19th May a HED calibration will be carried out.
  1107.  
  1108.      On 24th May A KEP in-flight calibration will be carried
  1109.      out.
  1110.  
  1111.      An Earth pointing manoeuvre will be carried out on 30th
  1112.      May.
  1113.  
  1114. 6.   GROUND SEGMENT
  1115.  
  1116.      The ground segment performed nominally during the
  1117.      reporting period with the exception of the problem at
  1118.      Goldstone reported above .
  1119.  
  1120.  
  1121.  
  1122. ULYSSES MISSION STATUS 5/17/93
  1123.  
  1124. PUBLIC INFORMATION OFFICE
  1125. JET PROPULSION LABORATORY
  1126. CALIFORNIA INSTITUTE OF TECHNOLOGY
  1127. NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
  1128. PASADENA, CALIF. 91109
  1129.  
  1130.  
  1131.                      ULYSSES MISSION STATUS
  1132.                           May 17, 1993
  1133.  
  1134.  
  1135.      All spacecraft and science operations are performing well. 
  1136. Ground-controllers are carrying out routine data-gathering
  1137. activities and experiment reconfigurations as required.  The 34-
  1138. meter (112-foot) and 70-meter (230-foot) ground antennas are
  1139. tracking the spacecraft as it continues to move farther south of
  1140. the ecliptic plane -- the plane in which the planets orbit.
  1141.  
  1142.  
  1143.      Earth-pointing maneuvers continue to be carried out about
  1144. every five days.  The last maneuver was performed on May 12,
  1145. 1993.
  1146.  
  1147.  
  1148.      Today Ulysses is about 683 million kilometers (424 million
  1149. miles) from Earth, traveling at a heliocentric velocity of about
  1150. 36,000 kilometers per hour (24,000 miles per hour).  The
  1151. spacecraft is now more than 30 degrees south of the sun's
  1152. equator.
  1153.  
  1154.  
  1155.                               #####
  1156.      Source:NASA Spacelink    Modem:205-895-0028  Internet:192.149.89.61
  1157. =--=--=-END-=--=--=
  1158.  
  1159. =--=END OF COLLECTION---COLLECTED 9 FILES---COMPLETED 21:33:21=--=
  1160.  
  1161.